A SWMS, or Safe Work Method Statement, is a short safety document for high risk construction work. It sets out the high risk work in the job, the hazards and risks that come with it, and how those risks will be controlled, before anyone starts.
You need a SWMS before you start any high risk construction work. In NSW and Queensland that comes from the Work Health and Safety Regulation: regulation 291 says what counts as high risk construction work, and regulation 299 says a SWMS has to be prepared before it starts.
These are the 18 kinds of high risk construction work in regulation 291:
One job can involve more than one. Digging a trench deeper than 1.5 metres with an excavator moving around it is trench work and powered mobile plant work. One SWMS covers both.
Not high risk construction work? You still have to manage the risks of the job, but the law doesn't ask for a SWMS. Many builders ask for one anyway.
At a minimum, a SWMS covers four things. Keep it short and plain, so everyone on the crew can follow it.
Which of the 18 kinds of high risk construction work the job involves. One job can involve more than one.
What could hurt someone on this job, on this site: live parts, heights, asbestos, trenches, traffic, plant, the weather on the day.
Work down the hierarchy of controls: get rid of the hazard if you can, then substitute, isolate, use engineering controls, then admin controls, and PPE last.
Who does what, how it's checked on site while the work is on, and when the SWMS gets reviewed.
A Tradietool draft also sets out the job details, the PPE, a risk rating for each hazard, the emergency plan (first-aider, nearest hospital, where everyone meets) and sign-on lines for the crew.
Say the job in 30 seconds, or type it. Tradietool picks out the high risk construction work, the hazards, the controls, the PPE and the emergency details, asks about anything missing, and lays it all out as a PDF. You check it and fix anything that doesn't match your site, send it to the PCBU to approve, and your crew sign on with a QR code.
Electrical SWMS are available now for NSW and Queensland. Plumbing, carpentry, scaffolding and other trades are coming soon.
Every SWMS is a draft. AI can get things wrong, so you and the PCBU check it against the site before work starts. Tradietool isn't legal or WHS advice.
Yes, for high risk construction work. The WHS Regulation in NSW and Queensland says a SWMS must be prepared before high risk construction work starts (regulation 299). For other construction work you still have to manage the risks, but the law doesn't ask for a SWMS. Many builders ask for one anyway.
The business doing the high risk construction work (the PCBU) makes sure it's prepared, in consultation with the workers who will do the job. On most small jobs that's the tradie's own business.
Not without checking it. A SWMS has to match the actual work, the site and the hazards on the day. A generic template reused without review won't reflect the job in front of you. Tradietool drafts a fresh SWMS for each job from your description of it.
Keep it until the high risk construction work is finished. If there's a notifiable incident, keep it for at least 2 years after the incident. If you change it, keep the old versions too.
No. It's a draft. Tradietool runs automatic checks on every draft, but AI can still get things wrong or miss things. You and the PCBU check it against the site, talk it through with the crew, fix anything that's wrong and approve it before work starts. Tradietool isn't legal or WHS advice.
Electrical SWMS are available now for NSW and Queensland. Plumbing, carpentry, scaffolding and other trades are coming soon. Other states are coming later. See how it works.
Tradietool is free while it’s in beta. Tell us what’s working and what’s not. It goes straight to the founder, and it shapes what we build next.